Tuesday, 17 May 2011

Finishing of leveling the floor joists & Sisalation

 Once we had finished up with leveling the flooring from yesterday, we moved on to rolling out the sisalation.  Best thing was to lay planks out on the joists that the roll of sisalation could be supported on.  A large metal pole was then put through the roll so that it could be rolled out easily.  As the weather was pretty windy today, we also had to be really careful with securing down the roll as quickly as possible so that it wasn't blown away - the paper rips very easily.  As the sisalation is rolled out over the floor joists, it neds to have a 100mm sag in the paper between the joists.  This was achieved by placing a piece of wood to this thickness onto a frame & dropping it down to get the sag (as pictured above).  Once at the right position, the sisalation was stapled down with a gun.  It is very important to keep the roll in a straight line.  We achieved this by laying out a string line with a measurement of 800mm from the joist center line (this is half the thickness of the particle board with 200mm to play with).  When laying out the sisalation, sections had to be cut out where the nogs were, so that there was some give.  It is really important when cutting the paper, it is done as accurately as possible, and any holes in the sisalation, or large gaps affects the ability of the sisalation to provide insulation.
It worked really well to have two people roll out, two to cut and staple the sisalation with the sag, and the third team to come behind to cut out squares of approximately 40 x 40mm in 300mm increments along the joist (this will be to allow the particle board to be glued down more effectively.  When the second line of sisalation is put down, the same process is used, and a new line is found to line up the roll with to keep it straight.  An overlap of the two lengths should also be created at a minimum of 100mm.


Monday, 16 May 2011

Nogs & checking joists are level

Today we kept on going with the nogs that we had started last week.  We split into teams to get different jobs done, as we are pretty behind at the moment because of the weather.  

Some of us, used the dumpy level to check the levels of the joists. Any discrepancies indicated areas that needed to be leveled out to be made plumb.  Essentially this was where the joists met on the middle bearer and also the middle sections of each joist where there is a bow.  Doing this, also indicated where there were problems with the bow of the wood, as it showed some had the bow down, instead of up.  These had to be changed around, as otherwise it won't support the loaded dimensions as well.  
A planer was also used in conjunction with a straight edge so that the joists and other areas were at the correct level.  This is so when the particle board is laid it sits flat throughout out the whole floor area.  Had to make sure that it was no more than 1-2mm lower than straight edge at all times, otherwise it only helps to cause discrepancies with the plumb of the floor, but in the opposite direction.
We also spent time to give extra bracing to the subflooring.  Stainless steel plates were placed on every join of the laminated bearers (on both sides).  These should be placed in the middle and have atleast 3 stainless steel nails on each side of the plate to keep it secure.   We also put bracing on from the bearers to the joist, as in the past we have had issues with the bearers staying behind on the jack studs when it is removed to be transported off the site.  Plates were also put on every joist join as well.
Bracing example with plate

Tuesday, 10 May 2011

Finishing Nogging, aligning joists & strengthening timber joins


Today we carried on from where we left off yesterday.  Still had loads of noggings to put into place along the sub-flooring.  Yesterday when we started on the nogs, Rich told us to miss out a spacing after attaching three of them. Found out today what the reasoning behind this was... having the spacing allowed us the possibility to adjust the joists that were going to have particle floor board attached to it, so that they run straight and are in alignment.  Using the string line, we ran this straight across the joists in question, then with a F clamp we moved the joist so that it became in line with this.  When it was centered, measurements were taken and a nog cut to the fit of this, so that when nailed in place, it would hold the joist at this setting.  If the joist had to pushed to achieve alignment, a larger nog was cut to push the joist into place.

We also strengthened any timber joins today with stainless steel nail plates.  These were placed over the join so that it was sitting evenly, then nailed into place with stainless steel nails.  These were done along the bearer joins (both on outside and inside edge joins) and also where the floor joists met along the middle bearer.   Also did some housekeeping of the site, had loads of rubbish bits of timber around, & also finally broke down the profiles that we had set up from DAY 1.  It seems like sub-flooring is fast coming to an end!!!

Still have a few more nogs to put in tomorrow, but hopefully we should be able to put flooring on by end of day

Monday, 9 May 2011

Finishing floor joists, boundary joists & starting noggings

Our house had a lot achieved today.  Team split up and did different jobs,  Some concentrated on attaching the last of the floor joists, and the others attached the boundary joists.  
With the boundary joists, it was important that they aligned with the stringline run out along the BL.  Where it didn't match up, clamps were used to hold in closer to the floor joists they were being attached to, so that they could be driven in closer.  The boundary joists had to be of H3.2 treatment as they were being exposed to outside air.  We had to be very careful with the lengths of timber we used for certain areas, as we only had a few of certain sizes so some thought really needed to put in to what we used where.  
For the nogging, measurements were made from the center bearer to 1800cr (as per joist plan).  An additional 22.5mm was added (half thickness of nog).  A stringline was run along this measurement so that the nogging could be aligned to it.  Got the tip from Rich to lay out a plank along the top of the joists, as it is much easier to hammer from above than at level or below.  From here the two floor joists having the nogging placed between it were clamped so that it held the nogging in place.  it was important that the nog sat flush with the face edge of both floor joists, & were squared off to the stringline.  3 x nails were driven straight from one side, the other were angled in at 3 spacings (careful not to hit any other nails).  This creates a strong attachment unlikely to move.   I only got a couple done as quite a time consuming job, would be better with someone to work with.
Another tip we learnt today was to hammer a piece of wood over the top of attached floor joists when the weather is wet.  This is because there is a tendency for the wood to twist and warp as it gets wet and then dry, having this in place will stop/minimise this from happening.

Left photo: Nogging aligned with string line and flush with face of floor joists
Right photo: Noggings between joists all attached.




Wednesday, 4 May 2011

Continuing with floor joist attachments


 Today we carried on with finishing off the floor joists that we started yesterday.  Had to remark a few measurements as they were slightly off, which set us back a bit, but other than that we did well.  When attaching it really becomes clear where the different areas are of the house, as the different treatments to the timber, define the wet areas to the other areas (pink is H1.2, other is H3.2).  Getting use to reading the plan and understanding where the joists go, which is good.  Had to go to one of the other houses that are nearing completion for some of the data though, as there are details missing that show where toilets sit and therefore where the waste will be.  Not knowing this information made it really difficult to work out the placement of the joints.  Definitely glad to have finished working that out.  Was pretty confusing.

Tuesday, 3 May 2011

Floor Joists


Moved on to attaching the floor joists today.  These were cut to length based on the plan for the house and were spaced according to this as well.  The boundary joist is laminated so that it is double the thickness, where as the ones within the boundary are single pieces of timber.
When doing the spaces we had to calculate where the toilet & shower area's were as the joist had to be shifted to allow for the pipes of these.  Also when laying out, we had to ensure the correct treated timber was placed in the right places.  Boundary joists and those joists underneath the wet areas needed to be treated at H3.2, and the rest of the area was H1.2.  The boundary areas needed this treatment as they are exposed to air, and the wet areas due to the fact that they will be able to withstand water if for some reason there was a leak in this area.
When attaching the floor joists, they needed to be lined up according to the BL, and flush to the lines marked along the bearer.  It is important that this is accurate, as otherwise the floor sheets will not have anything to sit on and be attached to. String lines were run down the length of the BL and depending on where abouts on the building they sat, the joists were lined up from this (as some lengths are longer and therefore closer to the BL than recessed areas for example).  When attached to the bearer, these were double nailed so they were stable, and bow was angled so the bow was up in the middle so when weight of house was on it, it would straighten out by flattening out.

Monday, 2 May 2011

Aligning bearers & bracing

Today we still had a bit to go on laminating bearers and getting them attached to the jack studs.  Once done, we had to align them so that they were sitting straight.  To do, we had to put a second batter board on the profiles and transfer the BL down on to it by using a level.  String lines were then run along the side of the bearer (doesn't really matter where, but mid way though width of bearer is good so its easier to work with).  Once the string line was set up, we moved into bracing the bearers, by securing it 30mm from string line.  We used a dodgem block that measured this in thickness and placed it between the bearer and string line - the bearer was then pulled or pushed to sit the block comfortably between the two.  The braces were then hammered into place to hold the bearers in the position.
When bracing the bearers, they spanned between the bearers.  Placed at an angle so one end is just under the bearer against a jack stud, and the other end is on the opposite side along the jack stud but at the base.  The braces we used were 3x2's, and can be cut to sit better by cutting a lip out so that it sits on the sole plate and won't slide out.  The opposite end is cut at an angle so there is no overhang.
The braces are spaced evenly along the bearers so that it is solid and holds in place.