Wednesday, 6 July 2011

Finishing Weatherboards & Putting Up Building Wrap

Today we put our heads down, so that we could get the weatherboards all painted & finished so that they would be dry and ready when we get back from break.
Had to do a bit of re-shuffling, as one of the frames collapsed under the weight - important to keep an eye on that in the future. 

Whilst doing this, some of the team started on the building wrap & by the end of day we were all out doing this to get the job done.  We stayed back till all the wrap was on the building, so that it was all covered up over the break.  As the floor board has been exposed for quite a period of time, it was a priority to get this done, to give them a bit of protection from the elements.
To put on the building wrap, the roll was run horizontally along the building & pulled as taunt as possible.  Once tight enough, it was secured using a staple gun to all frame work that it was sitting on. 
For areas that were irregular shapes (eg. the gable end roof truss) a craft knife was used to cut away to match the edge.  Blue strapping was then run around the outside of this building wrap to hold it in place (which again, was secured with a staple gun). 

Not openings were cut out except for the main door entry, the rest of the building is fully enclosed.


Tuesday, 5 July 2011

Weatherboard Painting - Oh Yeah.

 After finishing off the ceiling battens, we cleared out the 'living room' space of the house to prepare the area to paint the weatherboards under cover. 
At this stage, we also got rid of all of the temporary braces within the house (except for the ones up against the walls).
Once the floor area was clear, it was covered by building paper & stapled down (to provide an extra measure to decrease the amount of stain getting on to the floor sheets.  

A frames were then stood up & braced with a length of timber down the bottom to make the structure more stable.  The frames were also attached to the wall frame for extra support.The frames were then stacked up with weatherboards ready to be painted.
It is important to do this as it primes the weatherboard & helps to protect it from elements such as water.  The most important area to cover with the stain is the edges & grooved section where the boards butt up against each other.  This is because
the edges are most likely to be exposed to outside elements & the grooved section is subject to capilary action.  Once a weatherboard was fully painted on both sides, it was stacked up on the rack, with small wooden spacer blocks placed between each board so that it allowed them to dry better & so as not to disturb the paint on each board as well. 

Whilst we were doing this, some of the crew started putting the building wrap up around the house. 
As we are off on break after tomorrow, this is a good thing to doto try and help protect the particle & ply board on the floor of the building as it will stop the outside elements from getting in & sitting on the floor for long periods of time whilst we are not there. 

Monday, 4 July 2011

Roof Done... On To Ceiling Battens


Arrived on site today to see the roofs are finally up on the houses, pretty awesome to see.  Outside cladding on & from interior of building you can see the building wrap that they laid down before putting it on!
On to ceiling battens today.  Has been a pretty long process & still a little bit left to do tomorrow.  Basically started off day by nailing off battens already laid out on previous days.  75's used with the battens, where two needed to be secured in where ever it crossed under the bottom chord of the trusses.  Once done, we carried on with laying out the rest of the battens.  
To do, the spacings were marked out on the opposite sides of the room that it will be spanning.  A chalk line was used to mark this same measurement on all the bottom chords.  This is a good thing to do, as it means that aligning the batten is a lot easier as you have a mark to follow (rather than doing just by the 'eye').  
Once all marked out, the battens were cut to length.  They had to be cut so that the no two joins were adjacent to each other.  
Where there was a join on the truss, the batten had to be cut so that it fell mid way through the thickness of the bottom chord & then was nailed in with two skewed nails.   
When nailing in the battens, a helpful trick was to pre nail the fixings partially so that when it was held in place, it was easier to drive in. 
Another way to reduce work load was to secure an additional nogging on top of the double top plate, so that there was  surface to nail from the bottom upwards (rather than skewed from the side).  
The ceiling battens were laid out at 400mm spacings and varied from room to room where they fell (so they do not run in one line throughout the house as a result).


Wednesday, 29 June 2011

Workshop - Roofing Practical... Verge Construction

Unable to be on site today as the contractors are attaching the roofing today.  As a result the afternoon was spent in the workshop concentrating on the roofing exercise.  
As the gable end truss was attached yesterday, & we had started cutting to length the outriggers, we just continued on from here.  We still had a few to cut, so this took a fair amount of time.
The markings for spacing the outriggers and purlins were also transferred onto the rafters in question.  For the spacing of the outriggers, it was taken at 150mm from the apex.  At the bottom of the rafter, the outrigger was placed against a temporary vertical edge at the end of the rafter.  The outrigger was then put against this and was marked out (as the outrigger can not sit past the edge of the rafter).
The distance between the first and last outrigger was then measured and divided in half to give the middle outriggers position.  This process was repeated on both sides of the roof.  Purlins spacings also ascertained by following these same spacings, but not put on yet.  We did start on underpurlins though.
Outriggers were cut to 355mm (400 - 45mm)  which was the overhang + length to next rafter - thickness of the fly rafter.


Tuesday, 28 June 2011

Inspection Finishing Touches

Weather pretty crap today so really didn't spend much time on site at all. Main job was finishing off the roof edge protection from yesterday as it wasn't quite done by end of day.  
Also went around nailing in 100x3.75's at 500mm spacings through the double plate and down into the top plate.  This was done to show the inspector that we had used the correct fixings as the end of the nail pokes out of the bottom of the top plate and he is able to visibly see it has been fixed down without having to climb onto the frame to check.

Earlier on in the week, a small effort had been made to start running the ceiling battens, so a small amount of time today was spent on nailing them to the truss bottom chords that they run past, with 75's.  This is quite difficult as you are working at a strange angle, as you are having to hammer up... and it puts strain on your neck because you are looking up all the time... definitely not my most favourite job!

Rest of the time not on site, was spent in the workshop on the roofing exercise we started a week or so back.  We finally attached the gable end truss and started to cut to length the outriggers which was based on the length of the overhang (200mm), minus the thickness of the fly rafter.  We also were cutting the vertical struts to support the gable end truss and the additional loads that will be placed on it from the verge construction

Monday, 27 June 2011

Getting Ready For The ROOF...











Came back on site to find that the facias had been attached whilst we were away.  These were done by an outside contractor, & meant that we had a final finished product attached to the building.  As the material is quite soft and maliable, we now have to be pretty careful when working around it as we can easily bend it out of shape or knock it & dent/scratch it.
Today we concentrated on getting odd jobs done, as we still had loads to complete before the inspection & the roof is put up.
Nogs were still missing at the gable end trusses, so these had to be inserted, so that 70x35 timber ran underneath the top chord between every space.  Vertical struts also needed to be inserted at every point where a full length stud in the wall frame existed, so that this same line was run through the truss as well.  This was important to do so that there was a surface to attach the weatherboards to.

We also had a few bracing elements left to do.  This was mainly above the lintels where jack studs were present.  These had to be secured between the top plate through to the jack stud & onto the lintel.  As the jack stud was quite small and only held in by nails, it was impossible to secure the nail plates by hammering in... as it just forced the jackstud to push out of its correct position (which is flush with the lintel and the top plate).   As a result, Rich taught us a good trick to use, which was to use a clamp to push the nail plates in simultaneously with apposing forces.   
Some sections of the interior walls were missing double plates so these were also inserted in preparation for ceiling battens to be inserted.  When measuring these, they only had to be roughly measured as they only have to provide a surface for the battens to butt up against, or be at a length where battens could run between the spacings of the double top plate easily.  When securing the double plate, the exterior had to be flush with the wall so that there was a 50mm overhang into the inside of the building, and the interior double top plates had to sit even so that there was a 25mm overhang on each side.


The last job of the day was to put up the roof edge protection for the workers coming on site to put the roofing on.  Unitec is legally obliged to provide safety precautions for the workers, so these had to be put up.
The scaffold edging had to as close to the building line as possible (without touching as this can cause damage).  This was achieved by using the various connectors.  The first one used was an internal join, which sits on the inside of the tube &  

helps to connect another pipe to it so that a longer length can be achieved. 
The standards had to be no greater than 2.4m in spacings along the building edge & had to rise high enough to allow for a guard rail at 900mm in height above the lowest point of the  roof.
Once all standards had been attached around the perimeter of the building, the guard rails were then attached.  This was done by attaching swivel coupler at 900mm, 450mm & the lowest one, at a minimum of 150mm from the lowest point of the roof.  This provided a guardrail, midrail & bottom guardrail.  As the metal tubing was not long enough to reach the length of the building, these had to be joined together by using a sleeve (external joiner). 
Some of the standards were attached to existing scaffolding, so a single putlog coupler was used to achieve this.  
This had to be done around the whole of the perimeter of the building, including the gable end.


Wednesday, 22 June 2011

Purlin Time!

Today was purlin day.  First thing was that we prepared the trusses with marks showing the location of where the purlin would sit (based on the spacings specified in the plan.  These were scribed onto the trusses & also had a nail nailed into the area (so that the purlins could sit on the nails & stop it from sliding down the pitch of the roof).  Once all marked out, the purlins could start being laid out along the length of the building & attached.  From the apex of the building, the first measurement was 150mm on each side from the apex.  The joins of the purlins were done so that there were no two joins adjacent from each other, or
 on the same truss.  When getting the purlins to the correct length so that it always fell on a truss where a join could be, the purlins were cut to length up on the roof when laid out.  When it hit a truss where it could be cut, it was marked off to half the thickness of the rafter & then a hand saw was used to cut off at this mark.  It was then secured down with 2/100x375.  
This process gave more control on dictating where joins would fall whilst making it easier to do as it gave more leeway &  eliminated the chance of measurement errors (as apposed to cutting to length on the ground). 
As the purlins were being secured down, it was also really important that someone was at the gable end of the building, checking that it's alignment was ok.  This was really important 
as the roof cladding relies on the purlins being straight so that there is a surface for them to be fixed on to.
Once they are all laid on to the trusses, there will be several overhanging lengths off the gable end truss, these are all cut to length so that they are flush with the outriggers on the overhangs of the building.  Uplift fixings are then attached to the purlins, where 1x Z Wiredog was put on every point where a purlin met a truss, & 4 were attached where ever a join occurred on a truss.  

The purlins were also important as they provided an extra support surface to hold the ladder frame securely to the gable end truss.  This pre-nailed frame work was designed to cover the overhang & was attached by aligning it so that it was plumb with the gable end truss rafters.  Once in position a clamp was used to hold it in place & then it was secured with 100x3.75 galvanised flat head nails.